Living LARGE

Apollo Sheet Metal tackled  some huge ductwork at the Annacis Island Waste Water Treatment Plant Stage V Expansion – Phase I

By / Jessica Kirby  Photos courtesy of Apollo Sheet Metal

To say the FOA exhaust system at Annacis Island Waste Water Treatment Plant Stage V Expansion – Phase I required some high-level planning and consideration is an understatement to say the least—and this is not the project for understatements. The FOA exhaust system, which is pressure rated at -2.5 to -5 kPa, required ducting up to 84” in diameter and used three different material types—two of which you don’t necessarily learn about in sheet metal school. However, despite its challenges and learning curve, the project was a huge success, thanks to the skilled craftspersons at Apollo Sheet Metal in Coquitlam, who supplied and installed all components.  

The stainless steel FOA ductwork required more than 500,000 lb of 316 stainless steel, all fabricated in-house. The pipe/duct was up to 84” diameter, fabricated from 3/16” stainless plate, and the pipe supports were fabricated from 1/2” to 3/4” stainless plate. The pipe sections were assembled in up to 35’ long spool pieces, possible because of Apollo’s large fabrication plant with dual overhead cranes. Apollo used an electrochemical process to clean and passivate the welded joints on the stainless steel. 

The project also required approximately 1,200 linear feet of 30–36” SDR-17 high-density polyethylene (HDPE) FOA ductwork. HDPE at 36” weighs 100 lb per linear foot, and it was supplied in 50’ lengths, complete with electrofusion couplers. The pipe hangers and supports were fabricated from 3/4” stainless plate. 

The third material component was fiberglass reinforced plastic (FRP) FOA ductwork. The pipe was spooled and fabricated in China, shipped to Canada in containers, and detailed in Coquitlam by Apollo. The FRP duct is up to 84” in diameter and has a 5/16” wall thickness. 

The main challenge with the project was using materials that are outside of Apollo’s regular wheelhouse. HDPE and FRP required different techniques and additional learning, but the team was up for the challenge. Shawn Birdsell, Apollo’s site superintendent, said although working with those materials requires the same basic principles, there was a learning curve in understanding the process, tolerances, and other details. 

“With HDPE, the principles of round pipe apply, and we had a subcontractor do the electrofusion joints,” he says. “We relied on their experience, combined with our knowledge of what had to happen and how to install it. With the FRP, that was just duct wth flanges, but we had to deal with how to handle it, how heavy it is, and the logistics of having to order it from overseas, rather than ordering it from a local shop.” 

The sheer weight of these materials required special consideration in how to phase the project and of what equipment was required—just one piece of the 84-inch pipe weighed in at 9,500 lb.

“We had to get a bigger crane onsite just to do those pieces,” Birdsell says. “In sheet metal, you are usually doing lighter pipes with rigging or crank genies, and for one 35-foot piece to be just under 10,000 lb, it is highly unusual. You have to be sure everyone understands the safety requirements and make sure to not overload your slings on the rigging.” 

The team also worked hard to meet the strict requirements of hooking up to an existing plant. Because its work tied into the existing operational plant, Apollo had to work within small time allowances when the plant could undergo temporary shut down to certain sections.

“It is an operational waste water treatment plant, so we would get about four hours to rip out the old stuff and install our fitting,” Birdsell says.  “We have dealt with those kinds of logistics on past projects.” 

The weight, the size, and the learning curve may have been challenging, but having a strong crew made the project an overall success. “Having a good bunch of guys helped,” Birdsell says. “It is big stuff to build in the shop and truck out. Our shop did a great job of fabricating and shipping out the product, and the field was great at coordinating because we couldn’t do multiple pieces at once or deliver multiples in a day because of the size.”

Learn more about Apollo Sheet Metal at https://www.apollosheetmetal.com